Project: Concord-Carlisle High School

Summary of Project: 

This project will consist of 237,068 sq ft of new construction split between the main high school building (226,286 sq ft) and the alternate gym building (10,782 sq ft). The project will be built in one major construction phase comprised of sub-phases. These sub-phases include an enabling utility/limited site-work phase, new construction of two buildings, hazardous material abatement and demolition of existing buildings, and a site improvement phase. Concord-Carlisle High School will remain in operation during this project.

Amanti will perform the plumbing portion of this project.